13th March Update

The loco has finally been moved into the CTMS shed at Cranmore during the past week.  The windscreens have been fitted in No.2 cab meaning that glazing is now complete in that cab.  The only piece of glazing still missing is the No.1 cab secondmans side windscreen.
Inside the engine room, the supports for the replacement flexible mounts on No.1 exhauster have been completed.
Attention is also being given to a couple of the cant rail grilles that have been damaged.
The Air and Vaccuum Train Pipe governors have been removed for attention "off loco".